Villa Barr Park Concrete Paths
Villa Barr Park Concrete Paths
Updated: June 16, 2026
Start: May 1, 2026
Current Status: Pending
End: June 15, 2026
Description:
Concrete will be placed over the existing aggregate paths, as well as a new concrete loop around the existing pond to increase accessibility.

Traffic Control/Detours:
No detours will be necessary for this work. The park will be closed for approximately 30 to 45 days during the duration of this project.
Progress:
6/16/2026: The contractor will mobilize to the site this Tuesday and begin removing the topsoil in the locations of the proposed pathway. The overall project is anticipated to take approximately two weeks to complete.