ITC pathway and boardwalk connections to Bosco Fields

Updated: March 3, 2026
Start: February 2026
Current Status: In progress
End: May 15, 2026

Description:

Through MDOT's Local Agency Project office and federal funding program through SEMCOG ($230,000), the City will be constructing a pathway between the existing ITC Trail and Bosco

Fields Park. Construction will involve the placement of a hot-mix asphalt shared use path from the existing ITC Trail, south of 11 Mile Road, easterly to Bosco Fields Park, connecting to Beck Road, including approximately 600 feet of a 14-foot-wide boardwalk.

Traffic Control/Detours:

No detours or closures will be necessary for this project. A small area of the southwestern portion of Bosco Fields will be sectioned off for the staging of contractor equipment

Progress:

3/3/2026: This week, the tree subcontractor will begin to mobilize and start to remove the necessary trees, stumps and roots.