Start: June 2024
Current Status: Pending
End: Summer 2024
Description:
The contractor is scheduled to begin construction of 'Project 3' (below) after school lets out on June 7, 2024.
The City of Novi hired a contractor to rehabilitate Taft Road from the City's southern limits (Galway Drive) to 10 Mile Road and construct a new roundabout at the intersection of Taft Road and 9 Mile Road.
The project was split up into three projects:
Complete: Project 1 (2022) Roundabout at the 9 Mile and Taft Road intersection.
Complete: Project 2 (2023) Rehabilitate Taft Road from 10 Mile to the south City limits.
Pending: Project 3 (2024) Construct a new by-pass lane on the east side of Taft Road at the Addington Lane subdivision entrance.
Road Closure: TBD
Detour: TBD
Progress: Project 1, Project 2 are complete