Wixom Road Rehabilitation

Updated 5/15/24

Start: March 4, 2024
Current Status: In Progress
Projected End: Fall 2024
Road Jurisdiction: City of Novi

Description

The Wixom Road Rehabilitation Project includes almost two miles of asphalt resurfacing, adding a left turn lane from Kelsey Bay Dr. to Drakes Bay Dr., as well as a new concrete curb and gutter, storm sewer upgrades, and sidewalk ramp ADA upgrades.

Traffic on Wixom Road from Grand River to 10 Mile is northbound only and closed to southbound traffic.

More details will be made available here and sent via email to the Wixom Road Rehabilitation e-news group throughout the project. To be added to the e-news group and receive regular communication about this project, we simply ask that you click the link below to subscribe. 

CLICK HERE TO SIGN UP FOR WIXOM ROAD EMAIL COMMUNICATION

We thank you in advance for your patience as we make investments and improvements that will serve the community into the future. 

Road Closure

Throughout the project, one lane of northbound-only traffic on Wixom Rd. will be maintained between 10 Mile Rd. and Grand River. There will be no Southbound traffic allowed on Wixom Rd. during this project. Please follow the posted detour or use an alternate route. Residents living in the work zone on the side being worked on may have intermittent access to their driveways while work is directly in front of their homes.

Detour

The posted detour is east on Grand River; south on Beck Road; and west on 10 Mile Road. This project is expected to be completed in the Fall of 2024.

Progress

The paving contractor has finished placing the new leveling asphalt over the entire length of the southbound lane. Traffic is still northbound only but has been shifted onto the newly leveled southbound lanes. Curb and gutter removals began the week of May 13th on the northbound lanes.

This project is on track to finish in the fall of this year.