Neighborhood Road Program - Concrete

The City of Novi will be performing concrete road replacements (full reconstruction, rehabilitation and repairs) on the following street segments: South Lake Drive (West Park Drive to Sterling Drive); Sterling Drive (South Lake Drive to Cul-de-Sac); Serenity Drive (Iron side Court to Cul-de-Sac); North Hills Court (All); Darcey Court (All) and Broadmoor Park Boulevard (10 Mile to Broadmoor Park Lane).


The contractor, Mattioli Cement Company has completed all the streets in the 2018 program. All final punch list items are now complete. The contractor will revisit any remaining irrigation repairs in the spring of 2019.

Date of Substantial Completion: October 8, 2018

Street From To Subdivision
South Lake Drive West Park Drive Sterling Drive Bristol Corners
Sterling Drive South Lake Drive Cul-De-Sac (End) Bristol Corners
Serenity Drive Ironside Court Cul-De-Sac (End) Timber Ridge
North Hills Court Center Street Cul-De-Sac (End) North Hills Estates
Darcey Court 9 Mile Road Cul-De-Sac (End) Darcey Subdivision
Broadmoor Park Boulevard 10 Mile Road Broadmoor Park Lane Broadmoor Park